INTERNATIONAL PROCUREMENT GUIDE

Process Equipment Export Checklist from Türkiye

International equipment supply works best when technical responsibility, manufacturer identity, documents, packing and delivery terms are agreed before the purchase order.

Fabricated stainless steel process piping prepared for inspection and export
VESSORA TECHNICAL NOTEFor procurement and project teams

1. Build one controlled technical scope

Issue drawings, datasheets, equipment lists, material requirements, applicable standards and site conditions with a revision status. Ask the supplier to list deviations and exclusions rather than hiding them in general notes.

For multi-supplier packages, define battery limits, interface ownership and which party consolidates drawings, inspection records and packing lists.

2. Keep manufacturer and component brands transparent

Identify who fabricates tanks, piping and structural items. Pumps, valves, membranes, instruments and proprietary equipment should be listed by declared manufacturer and model or by an agreed approved-vendor rule.

This protects technical comparison, spare-parts planning and the buyer’s right to know the true origin of every major item.

3. Agree inspection and document milestones

Set drawing approval, material review, hold points, factory testing and final release milestones. Define whether the buyer, a third-party inspector or the supplier will sign each record.

Create a document register covering certificates, drawings, test reports, manuals, spare-parts lists, packing lists and any destination-specific conformity documents.

4. Match packing and Incoterms to the real route

Select the Incoterm, named place and insurance responsibility clearly. Check container or truck limits, over-dimensional cargo, port handling, moisture protection, lifting points, center of gravity and preservation period.

Shipping marks and packing lists must allow the site team to identify every crate, loose item and installation package without opening everything at once.

5. Plan site support before dispatch

Clarify whether the scope includes installation supervision, commissioning, performance testing, operator training, travel costs, local labor and tools. Agree remote support and warranty communication channels.

A technically complete shipment can still lose time if foundations, utilities, tie-ins, unloading capacity and site access were not checked before arrival.

Information to include.

  1. 01Controlled RFQ documents with revision status
  2. 02Deviation and exclusion list
  3. 03Named fabricators and declared component brands
  4. 04Approved drawing and document register
  5. 05Inspection, test and release plan
  6. 06Incoterm with exact named place
  7. 07Packing, preservation, lifting and shipping marks
  8. 08Commercial invoice, packing list and origin-related documents
  9. 09Site readiness, unloading and installation interfaces
  10. 10Commissioning, training, warranty and spare-parts route

Risks to remove early.

  • Comparing offers that do not share the same battery limits
  • Accepting unnamed component brands
  • Leaving destination documentation until cargo is ready
  • Using an Incoterm without an exact named place
  • Shipping before site interfaces and unloading are confirmed

Short answers for
project buyers.

Can equipment from several Turkish suppliers ship as one package?+

Yes, when technical interfaces, commercial responsibility, packing, documentation and consolidation arrangements are defined in advance.

Should the buyer know the actual manufacturer?+

Yes. Manufacturer and equipment origin should remain transparent, while Vessora coordinates the commercial, technical and export process.

Which Incoterm is best?+

There is no universal best term. The correct choice depends on route control, insurance, import capability, unloading responsibility and the buyer’s logistics resources.